Gridline

Britain's grid connection queue, counted once

Wind farms, solar parks and batteries can't supply power until the grid connects them, and thousands are waiting. The official lists overlap, so adding them up overstates the queue. Gridline links the lists and counts each project once.

Projects tracked
8,048
Registers combined
7
Latest release
26 Nov 2026
Capacity waiting to connect, November 2026Gigawatts (GW)
  1. Added up from the published lists736.8 GW

    Every project waiting on the two national lists and the 5 regional lists held so far.

  2. Staged wind farms counted once687.1 GW

    −49.7 GW. Hornsea 3 is listed at 2,250 MW and again at 3,000 MW. It is one 3,000 MW wind farm.

  3. Projects on two lists counted once663.4 to 674.5 GW

    −12.6 GW. Projects on both the national list and a regional one are kept once. Some links are certain, others likely, hence the range.

Partial: the regional list from National Grid Electricity Distribution (NGED) isn't held yet, so smaller projects in the Midlands, South Wales and the South West are missing. What's covered

Where projects are waiting

Local networks carry smaller projects area by area; the national grid carries large ones connected straight to transmission. Darker areas have more waiting. Hatched areas are missing a list, so their figures are too low.

UK Power Networks area: 13.9 to 14.9 GWNGED area: 2.1 GW, list incompleteSP Manweb area: 3.8 to 4.4 GWNorthern Powergrid area: 23.5 to 25.0 GWElectricity North West area: 8.4 to 8.7 GWSSEN southern England: 11.3 to 12.2 GWSouth Scotland: 7.9 to 11.5 GWNorth Scotland: 14.2 to 17.4 GW

102.0 to 113.0 GWwaiting in November 2026

Select an area to break it down by technology.

Ready to build, or not yet

Under the reformed connection rules, the national list sorts projects into two groups. Gate 2 projects have shown they are ready, for example by securing land, and keep their place in the queue. Gate 1 projects haven't yet.

Local networks, November 2026

Gate 2
4.5 GW
Shown they are ready; they keep their place.
Gate 1
19.3 GW
Not ready yet, so no firm connection date.
Not yet sorted
18.6 GW
On the national list without a gate.
Regional lists
59.5 to 70.5 GW
These lists don't record a gate.

How it works

  1. Archive every release

    The official lists overwrite themselves. Gridline keeps each release, twice weekly for the national list and monthly for the regional ones, so every change can be traced.

  2. Link projects across lists

    Matching rules give each project one ID across the national and regional lists. In a hand-checked sample, 98.6% of links are correct.

  3. Publish openly

    The dataset is rebuilt every day and free to download. This site is generated from the same files. Download the data

Built with Python and Polars for the data pipeline, and TypeScript with React Router for this site, served as static files from Cloudflare. View the source on GitHub.